48) A work performed at constant rate, it needs 4 workers to produce x units in 6 days, and how many workers are needed to produce 3x units in 4 days? 参考答案: 18 思路
以下是引用weiwu10在2003-10-30 19:48:00的发言: 48) A work performed at constant rate, it needs 4 workers to produce x units in 6 days, and how many workers are needed to produce 3x units in 4 days? 参考答案: 18 思路 请问一下,这题要如何算出的呢?
4 workers produce x units in 6 days ->4 workers produce x/6 units in 1 day ->1 worker produces x/24 units in 1 day
問3x units in 4 days ->1 worker produces x/6 units in 4 day so 3x除以x/6=18 [/face]