Which of the following are key elements in defining available-to-promise? I.It is uncommitted future inventory or capacity. II.It is calculated from the MPS. III.It is used for customer order promising. IV.It is used in make-to-stock and assemble-to-order companies.
A) I, II, and III B) I, II, and IV C) II, III, and IV D) I, II, III, and IV
You answered: D The correct answer is: A
Available-to-promise (ATP) is used with assemble-to-order and make-to-order companies to commit the uncommitted portion of a company's inventory or planned production.
---------------------------- why ATP can not be used in make-to-stock environment? |
|