标题: CPIM复习疑题求答
Which of the following are key elements in defining available-to-promise?
I.It is uncommitted future inventory or capacity.
II.It is calculated from the MPS.
III.It is used for customer order promising.
IV.It is used in make-to-stock and assemble-to-order companies.

A) I, II, and III
B) I, II, and IV
C) II, III, and IV
D) I, II, III, and IV

You answered: D
The correct answer is: A

Available-to-promise (ATP) is used with assemble-to-order and make-to-order companies to commit the uncommitted portion of a company's inventory or planned production.

----------------------------
why ATP can not be used in make-to-stock environment?
作者: yangchen0522    时间: 2012-2-4 22:16
嗯,好奇怪哦
作者: radiozhang    时间: 2012-2-5 17:16
答案错了吧?哪位大侠帮忙confirm。
作者: louder5488    时间: 2012-2-6 02:53
楼主,是不是有练习CPIM的软件啊?求提供链接
作者: evanyoung    时间: 2012-2-18 08:21
The whole volume inventory of MTS is "uncommitted" and is used to fulfill the customer needs. To some extent, you can view the entire inventory as "ATP", so there is no need to make a commitment cause you always got available stocks to back you up. Comparing to MTS, ATO & MTO start producing after the receipt of order, this is the case you need to check ATP to make a commitment to your customer.
作者: radiozhang    时间: 2012-3-17 17:50
Make sense. Thank you!
作者: iris198209    时间: 2012-6-20 16:47