标题: CPIM复习疑题求答 [打印本页] 作者: radiozhang 时间: 2012-2-3 22:09 标题: CPIM复习疑题求答 Which of the following are key elements in defining available-to-promise? I.It is uncommitted future inventory or capacity. II.It is calculated from the MPS. III.It is used for customer order promising. IV.It is used in make-to-stock and assemble-to-order companies.
A) I, II, and III B) I, II, and IV C) II, III, and IV D) I, II, III, and IV
You answered: D The correct answer is: A
Available-to-promise (ATP) is used with assemble-to-order and make-to-order companies to commit the uncommitted portion of a company's inventory or planned production.
---------------------------- why ATP can not be used in make-to-stock environment?作者: yangchen0522 时间: 2012-2-4 22:16
嗯,好奇怪哦作者: radiozhang 时间: 2012-2-5 17:16
答案错了吧?哪位大侠帮忙confirm。作者: louder5488 时间: 2012-2-6 02:53
楼主,是不是有练习CPIM的软件啊?求提供链接作者: evanyoung 时间: 2012-2-18 08:21
The whole volume inventory of MTS is "uncommitted" and is used to fulfill the customer needs. To some extent, you can view the entire inventory as "ATP", so there is no need to make a commitment cause you always got available stocks to back you up. Comparing to MTS, ATO & MTO start producing after the receipt of order, this is the case you need to check ATP to make a commitment to your customer.作者: radiozhang 时间: 2012-3-17 17:50
Make sense. Thank you!作者: iris198209 时间: 2012-6-20 16:47
刚决定参加CPIM的考试,请大家多多帮助啊