Schweser June 08 Exam 1 Afternoon
69. An analyst gathered the following data about a project:
The project's NPV is closest to:
A. -$144
B. $144
C. $279
D. $1,244
Why is the answer A? How to calculate it?
第一到五年的现金流$5000-$2000)*(1-40%)+($8000+$2000)/5 *40%=$2600
第0年的现金支出:CF0=-$8000-$2000=-$10000
CF1=CF2=CF3=CF4=CF5=$2600
I/Y=10 N=5 NPV=-$144
when you get the Net Income, you should add the non-cash charge, depreciation, back to net income to get the cash flow.
and then use calculator, follow the steps mentioned by the girl above~~