55.   (34557-!-item-!-188;#058&007575)

 

According to the Tristate Transportation Authority, making certain improvements to the main commuter rail line would increase ridership dramatically.  The authority plans to finance these improvements over the course of five years by raising automobile tolls on the two highway bridges along the route the rail line serves.  Although the proposed improvements are indeed needed, the authority's plan for securing the necessary funds should be rejected because it would unfairly force drivers to absorb the entire cost of something from which they receive no benefit.

 

Which of the following, if true, would cast the most doubt on the effectiveness of the authority's plan to finance the proposed improvements by increasing bridge tolls?

 

(A) Before the authority increases tolls on any of the area bridges, it is required by law to hold public hearings at which objections to the proposed increase can be raised.

(B) Whenever bridge tolls are increased, the authority must pay a private contractor to adjust the automated toll-collecting machines.

(C) Between the time a proposed toll increase is announced and the time the increase is actually put into effect, many commuters buy more tokens than usual to postpone the effects of the increase.

(D) When tolls were last increased on the two bridges in question, almost 20 percent of the regular commuter traffic switched to a slightly longer alternative route that has since been improved.

(E) The chairman of the authority is a member of the Tristate Automobile Club that has registered strong opposition to the proposed toll increase.

CD如何辨别

 答案是D


作者: aircavalry    时间: 2007-11-22 21:24

这是OG上的题吧。

C说开车的在政策实施之前买(可能有折扣的)代金券来推迟涨价带来的影响,但推迟并不意味着他们就不为修铁路买单了。

D说有20%的开车族绕道逃费,他们不会为不关系到自己利益的修铁路计划买单,所以是削弱。